Naitwar Mori HPS

 

Naitwar Mori Hydro Power Station with a generation potential of 60 MW is located on River Tons, a major tributary of River Yamuna in Uttarkashi district of  Uttarakhand State in North India. The project is designed as a standalone run of the river project. The entire project is on the right bank of river Tons stretching from Barrage site near village Naitwar and Power house complex near Bainol village. Naitwar Mori Hydro Power Station has the potential to generate 265.5 million units of electricity each year. A Memorandum of Understanding for execution of Naitwar Mori project was signed with the Government of Uttarakhand in November 21, 2005.

Hon’ble Union Minister of Power (Independent Charge) Sh. R K Singh and Hon’ble Chief Minister of Uttarakhand Sh. Trivender Singh Rawat laid the foundation stone of the Project at Mori on 30.03.2018.

All major works in 3 packages completed and both units of the project have been commissioned  as per following details.

Unit No.
 
Date of Synchronization
 
COD
 
Unit #1
 
14.11.2023
 
24.11.2023
 
Unit #2
 
29.11.2023
 
04.12.2023
 

Name of Component

Feature

Diversion Structure

Type

Barrage

Height

18.5 m

Length of barrage at top

50 m

Desilting Tank

Type

One, Twin Chamber

Size (in m)

130 (L) x 25 (W) x 13.5 (H)

Head Race Tunnel

Length

4.33 Km, Modified Horseshoe Type

Diameter

5.6 m (Finished)

Design discharge

73.5 m3/s

No. of Adits

02 nos.

Underground Surge Shaft

Height

57.33 m

Diameter

18 m

Pressure Shaft/ Penstocks

No. of Pressure Shafts

One (bifurcated into 2 branches)

Diameter of Pressure Shaft

4.0 m upto bifurcation, 2.8 m dia. of each branch

Length of pressure shaft

97.5 m upto bifurcation, 29 m length of each branch

Underground Power House

No. of units

02 (30 MW each)

Net design head

90.76 m

Type of turbine

Vertical Francis

Tail Race Tunnel

Shape

Modified Horse Shoe

Size

6.5 m (dia.)

Length

188 m

Tail Race Channel

Shape

Trapezoidal

Size

6.0 m wide at bottom & 17.5 m wide at top x 5.75 m (h)

The Project is financed on 70:30 debt equity ratio.

Sr. No.

Description

Date

1.

Execution Agreement between SJVN & GoUk

21.11.2005

2.

TEC of DPR

02.03.2010

3.

Environment Clearance

16.06 2016

4.

Stage-2 Forest Clearance

05.08. 2016

5.

Order regarding "Consent to Establish"

04.07. 2017

6.

Investment Approval

16.10. 2017

7.

Signing of Lease agreement for the forest land with Forest Deptt., GoUk

01.12. 2017

8.

Award of major Civil Works

05.12. 2017

9.

Foundation Stone of project

30.03.2018

10.

Award of Hydro Mechanical Package

18.04. 2018

11.

Award of Electro Mechanical Package

11.06. 2018

12.

Diversion of River

31.01.2019

13.

Complete HRT Excavation

05.07.2021

14.

Complete Power House Excavation

29.04.2022

15.

Boxing-Up of Unit-1

14.10.2022

16.

Completion of Surge Shaft Lining (i/c Grouting)

04.05.2023

17.

Boxing-Up of Unit-2

22.07.2023

18.

Completion of HRT lining

28.08.2023

19.

Reservoir Filling

16.09.2023

20.

Mechanical Spinning of Unit-1

27.09.2023

21.

Mechanical Spinning of Unit-2

24.10.2023

22.

COD (Unit-1)

24.11.2023

23.

COD (Unit-2)

04.12.2023

For Tariff Petition, please Click Here

For additional information in Tariff Petition of NMHEP filed before Hon'ble CERC, please Click here