- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2024 to March 2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October-2023 to March -2024
- Six Monthly Compliance Report for the period April- 2023 to September-2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of April, 2022 to September 2022
- Six Monthly Monitoring Report on Compliance to Environmental Aspects for the period from October, 2021 to March, 2022
- Six Monthly Monitoring Report on Compliance to Environmental Aspects (For period April, 2021 – September, 2021)
- Six Monthly Monitoring Report on Compliance to Environmental Aspects (For period October, 2020 - March, 2021) i.r.o Dhaulasidh HEP
- Half yearly Compliance report from April 2020 to September 2020
- Six Monthly Compliance report for the period of October 2019 to March 2020
- Request_Form_New
- Environmental Clearance
The Dhaulasidh Hydro Electric Project with capacity of 66 MW is located on river Beas, part of the Indus basin, in Hamirpur & Kangra districts of Himachal Pradesh. The project is designed as a Run of the River project with a small live storage that would be utilized for peaking power during the lean season.
The project holds potential of generating 304 million units of electric energy in a 90% dependable year.
Name of Component | Features |
| Diversion Dam | |
| Type | Concrete Gravity Dam |
| Height | 69.75 m |
| Total length of Dam at top | 195 m |
| Power Intake | 02 nos. |
| Diversion Tunnel | |
| Shape | D-shape |
| Diameter | 10.2 m |
| Length | 253 m |
| Penstock | |
| Type | Surface |
| Number | 2 |
| Diameter | 4.3 m |
| Length of each penstock | 60.50 m |
| Power House | |
| Type | Dam Toe power house on the Left Bank |
| Units | 2 (33 MW each) |
| Type of Turbine | Vertical Francis |
| Design Discharge | 161.34 m3/ sec |
| Gross Head | 45 m |
Tail Race Tunnel/Channel | |
| Type | Open Channel |
| Length | 69 m |
| Base Width | 15 m |
Investment Approval for an estimated cost of Rs. 687.97 crores accorded by GoI on 01.10.2020. The Project shall be financed on 80:20 debt equity ratio. Financial closure achieved on 18.04.2022.
S. No. | Description | Date |
1 | TEC from GoHP | 25.06.2011 |
2 | Stage-I Forest Clearance | 06.03.2012 |
3 | Environment Clearance | 21.02.2013 |
4 | Approval of CAT Plan | 01.10.2013 |
5 | Approval of revised cost estimate by GoHP | 11.05.2018 |
6 | Notification of SIA study issued by GoHP | 08.02.2019 |
7 | Submission of PIB memo to MoP | 18.07.2019 |
8 | Extension of FC-I by MoEF up to 01.11.2020 | 03.09.2019 |
9 | Signing of MoU with GoHP | 25.09.2019 |
10 | Forest Clearance Stage-2 by MoEF&CC | 11.08.2020 |
11 | PIB recommendations for Investment approval | 16.09.2020 |
12 | Investment Approval of project from GoI | 01.10.2020 |
13 | Award of EPC package for Civil and HM works | 06.05.2021 |
14 | Consent to Establish from HP State Pollution Control Board | 06.05.2021 |
| 15 | Foundation stone of project laid by Hon'ble Prime Minister | 27.12.2021 |