- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April 2025 to September 2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2024 to March 2025
- Six Monthly Environment Clearance for period April 2024 to September 2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October- 2023 to March-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2023 to September-2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Half-yearly compliance report for Environment for the period of April 2022-September 2022
- Half-yearly compliance report of Environment for the period of Oct 2021-March 2022
- Half yearly Compliance report from April 2021- September 2021
- Environment Clearance for the period from October 2020 to March 2021
- Half yearly Compliance report from April 2020- September 2020
- Half-yearly Compliance report of Environment from April, 2020 to September, 2020
- Half Yearly Compliance Report of environment for the periof of October 2019 - April 2020
- Environment Clearance
SJVN signed MoU with Bihar State Power Holding Company Limited and Bihar Power Infrastructure Company on 17.01.2013 for setting up Buxar Thermal Power Plant (2X 660 MW) in village Chausa, Distt. Buxar, Bihar. SJVN took over Buxar Bijli Company Private Limited on 04.07.2013 and changed name to SJVN Thermal Private Limited (a wholly owned subsidiary of SJVN Ltd.) on 17.10.2013. Power Purchase Agreement (PPA) has been signed with Bihar State Power Holding Company Limited for 85% share of power generation at Bus Bar rate.
Detailed Project Report of the project approved by East Central Railway, Hajipur on 05.09.2019. Environment Clearance has been received from MoEF & CC on 28.02.2017. Private land for main plant has been acquired. Clearance from airport authority for chimney has also been received. CCEA accorded investment approval for the project on 08.03.2019. Foundation stone was laid by Hon'ble Prime Minister of India on 09.03.2019. Main plant works have been awarded and are in progress.
Salient Features of Buxar Thermal Power Project | |
Location | Village Chausa, Distt Buxar, Bihar |
Installed Capacity | 1320 MW (2x660 MW) |
Annual Generation | 9828 Million Units |
Levelised Tariff | Rs. 4.19 per unit |
Estimated Cost | Rs. 10439.09 Crore at January 2018 PL |
Chimney | 2 nos. of 275m height |
Source of Coal | Long Term Coal Linkage from Coal India Ltd. |
Source of Water | River Ganga |
Cooling Tower | 2 nos. Induced Draft Cooling Tower each of 72,000 m3/ hr capacity |
Turbine | Single Reheat Condensing Type |
Transformer | 6 nos. single phase each of rated capacity 275 MVA, 20 kV |
Rail link (from project) | 14.84 Km (route length) |
S. | Description | Date |
1. | MoU with Bihar State Power Holding Company Limited (BSPHCL) and Bihar Power Infrastructure Company (BPIC) | 17.01.2013 |
2. | Acquisition of Buxar Bijli Company Private Limited | 04.07.2013 |
3. | Renamed as SJVN Thermal Private Limited (STPL) | 17.10.2013 |
4. | Environment Clearance by MoEF & CC | 28.02.2017 |
5. | Acquisition of Private Land ( 1058 acre) | 12.12.2017 |
6. | Completion of 33 KV line for construction power | 11.07.2018 |
7. | Issuance of LOA for coal linkage by CCL | 10.12.2018 |
8. | Investment approval of Project | 08.03.2019 |
9. | Foundation stone laid by Prime Minister of India | 09.03.2019 |
| 10. | Award of Main plant works | 22.06.2019 |
| 11. | DPR approved by East Central Railways | 05.09.2019 |
| 12. | Financial Closure | 16.03.2021 |
| 13. | PPA (Supplementary agreement) signed between STPL and BSPHCL | 09.04.2021 |
The Project is financed on 70 : 30 debt equity ratio.