image

Rampur HPS

Rampur Hydro Power Station of 412 MW installed capacity is located on River Satluj, a major tributary of Indus basin, in Shimla and Kullu district of Himachal Pradesh in North India. Rampur HPS is designed to generate 1878 million units of electricity each year. The plant is designed in tandem with run of the river plant Nathpa Jhakri (1500 MW) . A Memorandum of Understanding for execution of Rampur Project was signed between Government of India and Government of Himachal Pradesh on October, 2004. 

Major works project began in February 2007, after completion of HRT, Surge Shaft, Valve House, Power House, TRT and other associated works, water filling of water Conductor System completed in March, 2014 successfully without any leakage. 

The Project has been financed on a 70:30 debt equity ratio basis. The Project had the backing of World Bank. Estimated cost of the project at March, 2006 price level was Rs. 2047.06 crores.

Power generated from Rampur HPS is distributed to Northern Regional states i.e. Himachal Pradesh, Haryana, J&K, Punjab, Rajesthan, UP, Uttrakhand as per their percentage allocation by ministry of Power.

Six units of the project have been commissioned progressively till December, 2014 as per following details.

 

Unit No.
 
Date of Synchronization/ Commissioning
 
COD
 
Unit #1
 
19.03.2014
 
13.05.2014
 
Unit #2
 
21.03.2014
 
13.05.2014
 
Unit #5
 
30.03.2014
 
13.05.2014
 
Unit #4
 
12.06.2014
 
18.06.2014
 
Unit #3
 
31.07.2014
 
08.08.2014
 
Unit #6
 
04.12.2014
 
16.12.2014
 
  • The Rampur project is designed to work in tandem with the upstream 1500 MW Natpha Jhakri project.
  • Rampur project draws the outflow water from the larger upstream project.
  • A head race concrete line tunnel of 15.177 Km length with a 10.50 meter diameter.
  • A 165 meter high with a 38 meter diameter surge shaft that is open to the sky.
  • A Surface type valve house
  • A surface power house for 6 vertical Axis Francis turbines of 68.67 MW each to utilize a design head of 119.10 meters.
  • A 67.15 meter long with 10.50 meter diameter, horse shoe type and concrete lined tail race tunnel with an open channel.

Estimated cost at March 2006 Price Level with debt : equity ratio of 70 : 30 is Rs. 2047.03 Crores including interest during construction (IDC ) and financing charges ( FC ) of Rs. 260.41 Crores and Rs. 1.46 Crores respectively. Cost to completion is under approval of Govt. of India.

Important Events

 

Sr. No.DescriptionDate
1Date of signing of Implementation Agreement20.10.2004
2DPR Clearance by CEA09.12.2005
3Environment Clearance by MOEF31.03.2006
4Forest Clearance by MOEF07.04.2006
5PIB Clearance25.07.2006
6CCEA Clearance25.01.2007
7Award of Major Civil Works01.02.2007
8Award of Major Electro-mechanical Works16.09.2008
9Heading Excavation24.07.2013
10Benching Excavation20.02.2013
11Overt Lining19.08.2013
12Invert Lining24.11.2013
13Plugging Of Adit 
i)Kazo30.04.13
ii)Kunni22.02.14
iii)Kasholi20.02.14
iv)Goshai23.01.14
v)Bayal21.02.14
14Surge Shaft 
i)Pilot Excavtion31.01.2009
ii)Winding08.04.10
iii)Lining31.08.12
iv)Gate Erection25.02.14
15Penstock 
i)Fabication31.05.12
ii)Erection12.03.14
16BVH30.11.13
17GIS04.04.13
18Power House30.09.13
19DT Gate25.01.14
20Collection Gallery31.05.13
21TRT Out Fall31.05.13
i)Gate Erection26.03.14
22HRT Filling 
i)Start23.02.14
ii)Finish14.03.14

 

23Boxing UPSpiningSynchronizationCOD
Unit#131.01.1304th MAR-1419th MAR-1413th MAY-14
Unit#226.02.1305th MAR-1421st MAR-1413th MAY-14
Unit#304.01.1409th JUL-201431st JUL-1408th AUG-14
Unit#412.09.1328th MAY-1412th JUN-1418th JUN-14
Unit#527.04.1323rd MAR-1430th MAR-1413th MAY-14
Unit#619.06.1320th APR-1404th DEC-1416th Dec-14