- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October 2024 to March 2025
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2024 to September-2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period October -2023 to March 2024
- Six Monthly Compliance Report of conditions stipulated in the Environment Clearance for period April- 2023 to September -2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of October, 2022 to March 2023
- Six Monthly Monitoring Report on Compliance to Environment Aspects for the period of April, 2022 to September
- End Term Impact Evaluation of Resettlement Action Plan & Community development Activities
- Technical Education for Local Youth
- Acquisition of Private Land
- Executive summary
- Final Executive summary
- Social Assessment Report
- Sustainable Communality Development Programme
- Resettlement Action Plan for RHEP
- Monitoring of R&R activities of RHEP
- Progress Report on R&R
- Technical Education for Local Youth of Rampur HEP
- Mid-Term Impact Evaluation of the RAP Implementation and Community Development Activities
Rampur Hydro Power Station of 412 MW installed capacity is located on River Satluj, a major tributary of Indus basin, in Shimla and Kullu district of Himachal Pradesh in North India. Rampur HPS is designed to generate 1878 million units of electricity each year. The plant is designed in tandem with run of the river plant Nathpa Jhakri (1500 MW) . A Memorandum of Understanding for execution of Rampur Project was signed between Government of India and Government of Himachal Pradesh on October, 2004.
Major works project began in February 2007, after completion of HRT, Surge Shaft, Valve House, Power House, TRT and other associated works, water filling of water Conductor System completed in March, 2014 successfully without any leakage.
The Project has been financed on a 70:30 debt equity ratio basis. The Project had the backing of World Bank. Estimated cost of the project at March, 2006 price level was Rs. 2047.06 crores.
Power generated from Rampur HPS is distributed to Northern Regional states i.e. Himachal Pradesh, Haryana, J&K, Punjab, Rajesthan, UP, Uttrakhand as per their percentage allocation by ministry of Power.
Six units of the project have been commissioned progressively till December, 2014 as per following details.
| Unit No. | Date of Synchronization/ Commissioning | COD |
| Unit #1 | 19.03.2014 | 13.05.2014 |
| Unit #2 | 21.03.2014 | 13.05.2014 |
| Unit #5 | 30.03.2014 | 13.05.2014 |
| Unit #4 | 12.06.2014 | 18.06.2014 |
| Unit #3 | 31.07.2014 | 08.08.2014 |
| Unit #6 | 04.12.2014 | 16.12.2014 |
- The Rampur project is designed to work in tandem with the upstream 1500 MW Natpha Jhakri project.
- Rampur project draws the outflow water from the larger upstream project.
- A head race concrete line tunnel of 15.177 Km length with a 10.50 meter diameter.
- A 165 meter high with a 38 meter diameter surge shaft that is open to the sky.
- A Surface type valve house
- A surface power house for 6 vertical Axis Francis turbines of 68.67 MW each to utilize a design head of 119.10 meters.
- A 67.15 meter long with 10.50 meter diameter, horse shoe type and concrete lined tail race tunnel with an open channel.
Estimated cost at March 2006 Price Level with debt : equity ratio of 70 : 30 is Rs. 2047.03 Crores including interest during construction (IDC ) and financing charges ( FC ) of Rs. 260.41 Crores and Rs. 1.46 Crores respectively. Cost to completion is under approval of Govt. of India.
Important Events
| Sr. No. | Description | Date |
|---|---|---|
| 1 | Date of signing of Implementation Agreement | 20.10.2004 |
| 2 | DPR Clearance by CEA | 09.12.2005 |
| 3 | Environment Clearance by MOEF | 31.03.2006 |
| 4 | Forest Clearance by MOEF | 07.04.2006 |
| 5 | PIB Clearance | 25.07.2006 |
| 6 | CCEA Clearance | 25.01.2007 |
| 7 | Award of Major Civil Works | 01.02.2007 |
| 8 | Award of Major Electro-mechanical Works | 16.09.2008 |
| 9 | Heading Excavation | 24.07.2013 |
| 10 | Benching Excavation | 20.02.2013 |
| 11 | Overt Lining | 19.08.2013 |
| 12 | Invert Lining | 24.11.2013 |
| 13 | Plugging Of Adit | |
| i) | Kazo | 30.04.13 |
| ii) | Kunni | 22.02.14 |
| iii) | Kasholi | 20.02.14 |
| iv) | Goshai | 23.01.14 |
| v) | Bayal | 21.02.14 |
| 14 | Surge Shaft | |
| i) | Pilot Excavtion | 31.01.2009 |
| ii) | Winding | 08.04.10 |
| iii) | Lining | 31.08.12 |
| iv) | Gate Erection | 25.02.14 |
| 15 | Penstock | |
| i) | Fabication | 31.05.12 |
| ii) | Erection | 12.03.14 |
| 16 | BVH | 30.11.13 |
| 17 | GIS | 04.04.13 |
| 18 | Power House | 30.09.13 |
| 19 | DT Gate | 25.01.14 |
| 20 | Collection Gallery | 31.05.13 |
| 21 | TRT Out Fall | 31.05.13 |
| i) | Gate Erection | 26.03.14 |
| 22 | HRT Filling | |
| i) | Start | 23.02.14 |
| ii) | Finish | 14.03.14 |
| 23 | Boxing UP | Spining | Synchronization | COD |
|---|---|---|---|---|
| Unit#1 | 31.01.13 | 04th MAR-14 | 19th MAR-14 | 13th MAY-14 |
| Unit#2 | 26.02.13 | 05th MAR-14 | 21st MAR-14 | 13th MAY-14 |
| Unit#3 | 04.01.14 | 09th JUL-2014 | 31st JUL-14 | 08th AUG-14 |
| Unit#4 | 12.09.13 | 28th MAY-14 | 12th JUN-14 | 18th JUN-14 |
| Unit#5 | 27.04.13 | 23rd MAR-14 | 30th MAR-14 | 13th MAY-14 |
| Unit#6 | 19.06.13 | 20th APR-14 | 04th DEC-14 | 16th Dec-14 |